Walnut Creek Desilt Project

General work description: The work to be done generally consists of removing approximately 115,000 cubic yards of channel material from designated areas of Walnut Creek Channel roughly 2,000 feet north of Concord Avenue to roughly 3,000 feet south of Concord Avenue. Work also includes placing a stake and tape boundary between the designated area and environmentally sensitive areas, traffic control, construction of temporary access ramps, portable message signs, hydroseeding, and pre-construction and post-construction surveying.
GFE (click to expand/collapse)
Name Size
CCC_GFE_8334 1.3 MB
Informational Handout (click to expand/collapse)
Download section as a Zip file free of charge
Name Size
Sediment Sampling and Analysis Letter Report-Ninyo 9.2 MB
Walnut Creek Desilting_SAP Implementation_11.28.2022 full 18.0 MB
Proposal & Contract (click to expand/collapse)
Name Size
CCC_PC_8334 840.9 KB
Special Provisions (click to expand/collapse)
Name Size
CCC_SP_8334 47.8 MB